                                                The 12,000 ton press.


       The structural work required raising the bay roof from 40 to 87ft and, as always with
       maintenance and modification at the factory, this roofing work was undertaken during the
       summer  holiday  shutdown.  When  the  workforce  returned  the  raised  section  had
       corrugated sheet fixed on the top, but not yet to the sides, and needless to say it rained.
       The night of August 16, 1952, however, had no ordinary rainstorm, delivering as it did the
       terrible flooding experienced particularly at Lynmouth. Goodness knows how much water
       came through the roof at HDA that night.